Boudh is well connected with road and rail with other district headquarter and the state capital Bhubaneswar. The distance of Boudh from Bhubaneswar is 240 Km. One can come to Boudh via State Highway No. 1 & 14 ( via Nayagarh –Charichhak) or can come by National Highway No. 42 . ( via- Angul).Regular train services are available from Bhubaneswar viz. Bhubaneswar – Sambalpur Intercity Express,Hirakud Express,Puri-Sambalpur passenger train. To reach Boudh one has to get down at Rairakhole station. From here one has to travel around 27 Km. either by Bus or taxi to reach Boudh. The nearest Airport is at Bhubaneswar.
NATIONAL HIGHWAY
Executive Engineer, National Highway Division, Bolangir is in-charge of Construction Development and maintenance of following Kms. Of National Highways passing through Boudh District
1.N.H.224 from Km. 137/809 to 249/00 = 111.091 Km. (Banigochha to Manamunda Bridge Chhak)
New N.H. 51/0 Km to 162/091 (Manamunda Bridge Chhak to Banigochha)
Details of the on-going works and works to be taken up is furnished below.
|
Sl No. |
Name of the Project |
Total Kms. |
Name of the Agency |
Date of commencement |
Estimated Cost (in Lakhs) | Expenditure incurred (in Lakhs) |
Expected date of completion |
Remarks |
|
1 |
2 |
3 |
4 |
5 |
8 |
9 |
||
|
1 |
Widening & strengthening from Km 137/809 to 159/000 (Vill-Banigochha to Nuagaon) |
21.19 |
- |
- |
- | - |
- |
Survey work is under progress. The work will be implemented out of World Bank finance. The worst patches 3 Km repaired out of P.R. Grant in the Financial Year. |
|
2 |
Widening & strengthening from Km 159/000 to 184/260 (Vill- Nuagaon to Nuapada) |
25.26 |
A.R.S.S- ATLANTA (JV) |
30.08.2010 |
8155.88 | 1203.64 |
29.08.2012 |
Embankment formation work is under progress 6.5 Km widening work completed. |
|
3 |
Widening & strengthening from Km 184/260 to 191/000 (Vill- Nuapada to Radhanagar) |
6.740 |
R.K.D. Construction Pvt. Ltd. |
01.09.2008 |
1383.81 | 1092.98 |
31.05.2011 |
6.5 Km of Blacktop surface completed. Rest 0.24 Km will be completed with in June-2011. |
|
4 |
Widening & strengthening from Km 191/000 to 198/000 (Vill- Radhanagar to Raithani) |
7.0 |
Sri Durga Condev Pvt Ltd. |
07.09.2007 |
1211.66 | 1211.66 |
- |
Completed in all respect. |
|
5 |
Widening & strengthening from Km 198/000 to 205/000 (Vill- Raithani to Boudh Fishery Office) |
7.0 |
East India Construction Company |
06.10.2007 |
1143.70 | 1143.70 |
- |
Completed in all respect. |
|
6 |
Widening & strengthening from Km 205/000 to 211/000 (Vill- Boudh Fishery Office to Khuntabandha) |
6.0 |
ARSS Infrastructure Pvt. Ltd. |
26.02.2009 |
1266.31 | 712.30 |
31.05.2011 |
5.4 Km B.T. surface completed. Balance 600m is under progress, which will be completed during June-2011. |
|
7 |
Widening & strengthening from Km 211/000 to 218/000 (Vill- Khuntabandha to Talibandh) |
7.0 |
Sri Durga Condev Pvt Ltd. |
26.08.2009 |
1338.64 | 930.50 |
31.05.2011 |
5.5 Km B.T. and 1.5 Km widening work has been completed. Balance will be completed during June-2011. |
|
8 |
Widening & strengthening from Km 218/000 to 224/000 (Vill- Talibandh to Singari) |
6.0 |
ARSS Infrastructure Pvt. Ltd. |
25.08.2009 |
1135.24 | 602.26 |
31.05.2011 |
5.5 Km B.T. surface completed. Balance 0.5 Km is under progress, which will be completed during June-2011. |
|
9 |
Widening & strengthening from Km 224/000 to 249/000 (Vill- Singari to Manamunda) |
25.0 |
ARCONS Infrastructures & constructions Pvt Ltd |
08.09.2010 |
6881.62 | 160.00 |
07.09.2012 |
The work has been started. Embankment Work is under progress. |